Schedule
The scheduling for this project comes in the form of a Gantt chart, as shown in figures E01 and E02. Over the course of winter quarter, it became widely apparent that meeting deadlines set during fall quarter would become difficult due to unforeseen delays and much longer production times than expected. As a result of this several components were produced late, but manufacturing progress still met class deadlines. In the second week of March, a completed device is to be presented and functional in preparation for the testing process next quarter.

Figure E01-Project Gantt Chart

Figure B01-Project Gantt Chart

Figure B02-Project Gantt Chart Cont.